Belém Cultural Center Modernizes Theaters and Museum With 3.1 Million Euros From Recovery Plan
The Belém Cultural Center modernizes theaters and museum with 3.1 million euros from the Recovery and Resilience Plan.
- The Belém Cultural Center modernizes theaters and museum with 3.1 million euros from the Recovery and Resilience Plan.
- The investment, funded 100% by the Recovery and Resilience Plan, covers the theater, the Contemporary Art Museum, the building, and meeting rooms.
- The theater received 1.3 million euros, while the museum received 1.1 million euros.
Investment and Funding
The Belém Cultural Center (CCB) invests 3.1 million euros, with funding from the Recovery and Resilience Plan (PRR), to modernize the theaters, the museum, and several technical facilities, including lighting and stage equipment.
The investment, funded 100% by the PRR through the Cultural Heritage Safeguarding Fund, covers interventions in the theaters, the Contemporary Art Museum (MAC/CCB), the building, and meeting rooms.
Theaters and Museum
Theaters received 1.3 million euros, including theater lighting and room lighting renovation and the stage bar command system. The museum received 1.1 million euros for climate control, technical management, and lighting.
The remaining interventions cover exterior lighting, the Luís de Freitas Branco room, and meeting room video equipment. The works also include renovations from 2021 to 2025, such as the MAC/CCB reception area and the performance center facades and roof.
The Theater and the Museum
The theater received 1.3 million euros, including theater lighting and room lighting renovation and the stage bar command system.
One of the most relevant interventions was the replacement of the electronic command system of the 35 bars of the large theater, at a cost of 290 thousand euros, while keeping the existing mechanical structure.
These bars, which suspend lighting, scenery, screens, and the acoustic shell, have a load capacity of 600 kilos each and are installed over the stage where artists and technicians work, constituting a critical safety infrastructure.
The previous command system was from 2012 and no longer had technical support from the manufacturer, which raised safety concerns.
The works process lasted 12 months, involving six contracts launched by public tender and divided into ten lots.
The deadlines and prices were met, with the contracts awarded at values about 8% below the base prices.
The intervention in the large theater lasted five to six weeks in August, taking advantage of the programming interruption without any show cancellations.
The CCB president, Nuno Vassallo e Silva, showed the PRR investment results during a visit on November 19.
The CCB technical director, João Pimentel, explained that the command system replacement allowed to anticipate a possible failure that could interrupt a show.
The previous command system was from 2012 and had lost manufacturer technical support.
The large theater room has a capacity of 1500 seats and receives opera, theater, and music shows.
The 290 thousand euro investment only covered the command system, keeping the mechanical component in good condition.
The change to LED covered theater and room lighting.
The CCB Buildings and Technical Installations director, João Pimentel, explained that the work required very intense preparation from the technical teams.
The CCB president, Nuno Vassallo e Silva, said that only the bars were mentioned due to safety issues.
Glossary
- Recovery and Resilience Plan — The university's budget for 2026 was set at €356.8 million. In 2025, transfers from the state budget for current expenditure amounted to €169 million and covered 84% of staff costs; in the same year about €30 million of investment in student housing was under way, partly financed by Portugal's Recovery and Resilience Plan.
- Contemporary Art Museum — 2020 PLAYER OF BEINGS, Ming Contemporary Art Museum, Shanghai 2019 The Return of Guests – Selections from the PSA Collection Shanghai Contemporary Art Museum, Power Station of art, Shanghai
- public tender — The maintenance of Lisbon's funiculars had been outsourced since 2011. The last public tender for maintenance was opened in 2022, to which four companies applied, after which Carris signed a contract with MAIN – Maintenance Engineering, worth €1 million, covering the Glória, Bica, and Lavra funiculars, as well as the Santa Justa Lift. According to the Carris workers' union, the company's employees had repeatedly reported poor maintenance work by MAIN.