Federal Government Commissions Electricity Infrastructure Projects in Gombe State

Federal Government commissioned electricity infrastructure projects in Gombe State including a new substation in Billiri and upgraded transformers at the Gombe Transmission Substation.

Key points
  • The Federal Government commissioned a new 120MVA transmission substation in Billiri, Gombe State.
  • The Federal Government upgraded the Gombe Transmission Substation with a 300MVA and a 100MVA power transformer.
  • The upgrades are expected to provide additional capacity for electricity consumers and accommodate more than 70,000 additional households.

The Federal Government commissioned electricity infrastructure projects in Gombe State on Wednesday, November 19, 2026. The Minister of Power, Joseph Tegbe, conducted the commissioning ceremony for the new 120MVA transmission substation in Billiri. Additionally, the Minister oversaw the commissioning of upgraded transformers at the Gombe Transmission Substation. These infrastructure improvements aim to bolster the region's power supply capabilities significantly.

Infrastructure Commissioning Details

The new 120MVA transmission substation in Billiri has an installed capacity of 120MVA. This capacity is equivalent to approximately 96 megawatts of power generation potential. The Billiri substation is configured with two 60MVA transformers. These transformers connect directly to the existing Gombe–Zabana–Yola transmission line to facilitate power distribution.

The Federal Government also upgraded the Gombe Transmission Substation with new equipment. A 300MVA power transformer was installed at the Gombe facility. This installation doubled the upstream transmission capacity from 300MVA to 600MVA. This increased upstream capacity is equivalent to 480 megawatts of power transmission capability.

Gombe Substation Upgrades

Further enhancements were made to the Gombe Transmission Substation during the commissioning. An existing 30MVA transformer was replaced with a 100MVA transformer. This replacement increased the downstream transformation capacity to 220MVA. This new downstream capacity is equivalent to 176 megawatts of power distribution capability. These upgrades significantly boost the regional power grid resilience and operational efficiency.

The Billiri substation features six outgoing 33kV feeders. These feeders connect to the existing Gombe-Savannah-Yola transmission line. The World Bank funded the Billiri substation project. Chris Ejik International Limited executed the construction and installation of the new substation infrastructure. The Minister of Power stated that these projects reflect President Bola Tinubu’s commitment to strengthening the national grid infrastructure.

Projected Benefits and Government Response

These infrastructure upgrades are expected to provide additional capacity for electricity consumers across the region. The enhancements are projected to accommodate more than 70,000 additional households with reliable power access. The Minister of Power stated that the new 120MVA substation will strengthen the economic foundation of host communities. Furthermore, these projects will stimulate businesses, attract investment, and create employment opportunities within the local economy.

Governor Muhammadu Inuwa Yahaya of Gombe State represented by Commissioner for Energy and Mineral Resources, Sanusi Ahmed Pindiga, expressed gratitude during the ceremony. The Governor thanked President Bola Tinubu for assenting to the Electricity Act 2023. The Commissioner for Energy and Mineral Resources stated that the new 300MVA transformer doubles upstream capacity to 600MVA. The Commissioner also noted that replacing the old 30MVA unit with a 100MVA transformer increases downstream capacity to 220MVA. The Minister of Power stated that the growing electricity demand exceeded the capacity of the existing infrastructure, resulting in suppressed demand across the region.

Glossary

  • World Bank — The World Bank is an institution that was established in 1944 and since 1958 has provided Nigeria with low interest rate loans and grants through the International Development Association(IDA) and International Bank for Reconstruction and Development (IBRD). As of 2018, it consists of 189 member countries.
  • MVA — The new 120MVA transmission substation in Billiri has an installed capacity of 120MVA. This capacity is equivalent to approximately 96 megawatts of power generation potential.
  • megawatts — This capacity is equivalent to approximately 96 megawatts of power generation potential. This increased upstream capacity is equivalent to 480 megawatts of power transmission capability.
  • kV feeders — The Billiri substation features six outgoing 33kV feeders. These feeders connect to the existing Gombe-Savannah-Yola transmission line.
  • President Bola Tinubu — The Minister of Power stated that these projects reflect President Bola Tinubu’s commitment to strengthening the national grid infrastructure. The Governor thanked President Bola Tinubu for assenting to the Electricity Act 2023.
Read on News Nigeria ›