Tuesday, November 24, 2026Last updated 84 countries · 60 languages · Updated every 10 minutes · Original link with every article
☰ All menus
Editorial principlesTipsRSS
🌐 English ▾

NEWS WORLD

EnglishNews from 84 countries in 60 languages

London
🌐60
Key indicators
Delayed quotes

Latvian Government Approves Prefabricated Bridge Structure for Riga Renovation

Latvian government approved prefabricated bridge structure for Riga renovation. The Riga municipality must still decide on the structure.

Key points
  • The first interdepartmental commission meeting for the Vanšu Bridge renovation took place on November 19, 2026.
  • The Latvian government decision allows the Riga municipality to receive a prefabricated bridge structure from state material reserves.
  • A cautious scenario suggests the temporary bridge construction could complete by spring 2028.

The first interdepartmental commission meeting for the Vanšu Bridge renovation took place on November 19, 2026. During this meeting, Edgars Bergholcs was elected as the commission chairman, and Ansis Pūpols was elected as the deputy chairman. The Latvian government decision allows the Riga municipality to receive a prefabricated bridge structure from state material reserves during the renovation process. The Riga municipality has not yet decided whether to utilize this possibility for the temporary bridge structure.

Bridge Structure Procurement

Latvijas valsts ceļi is currently amending the contract for the prefabricated bridge structure production. The manufacturer has promised to produce the bridge structure within seven to eight months. The state will provide only the bridge deck; the Riga municipality must procure the bridge piers and auxiliary structures separately. Mārtiņš Lazdovskis stated that the state is purchasing 540 meters of high-load-bearing bridge structure. This bridge structure can be combined in various ways depending on the load requirements for the temporary crossing.

Technical Design and Traffic Flow

For lighter loads, such as those suitable for passenger cars, the bridge length can be extended up to 900 meters. A cautious, realistic scenario suggests that the technical design and construction of the temporary bridge over the Daugava River could be completed by spring 2028. During the meeting, Edgars Bergholcs presented a traffic flow map for the right bank of the Daugava. He also discussed various traffic diversion options to manage the flow during the construction period.

Commission Meeting Details

The commission chairman, Edgars Bergholcs, presented the traffic flow map for the right bank of the Daugava during the November 19, 2026, meeting. The commission's deputy chairman, Ansis Pūpols, participated in the discussions regarding the temporary bridge solutions. The Riga City Council's Department of Urban Space and Mobility was not invited to the meeting despite possessing traffic flow data for the Vanšu Bridge and surrounding streets. The state is purchasing 540 meters of high-load-bearing bridge structure. The Riga municipality must procure the bridge piers and auxiliary structures separately from the state-provided bridge deck. The commission chairman, Edgars Bergholcs, presented a traffic flow map for the right bank of the Daugava during the November 19, 2026, meeting.

Glossary

  • Vanšu Bridge — The Vanšu Bridge is a structure undergoing renovation. The commission chairman presented a traffic flow map for the right bank of the Daugava during the November 19, 2026, meeting.
  • Riga municipality — The Riga municipality has not yet decided whether to utilize the possibility of receiving a prefabricated bridge structure from state material reserves during the renovation process. The Riga municipality must procure the bridge piers and auxiliary structures separately.
  • state material reserves — The Latvian government decision allows the Riga municipality to receive a prefabricated bridge structure from state material reserves during the renovation process. The state will provide only the bridge deck.
  • bridge piers — The Riga municipality must procure the bridge piers and auxiliary structures separately. The state will provide only the bridge deck.
  • auxiliary structures — The Riga municipality must procure the bridge piers and auxiliary structures separately. The state will provide only the bridge deck.
Read on News Latvia ›